Trading floor installation delivered in phases to minimise disruption for a busy business.

Barclays Northampton - Trading Floor Desk Installation

Phased installation of 2,000 sit-stand desks across 10 floors for Teknion at Barclays' Northampton site, coordinating power, data and storage without disrupting their busy trading floor.

Key benefits:

  • Client: Teknion
  • Location: Barclays, Northampton
  • Programme: 8 phases across 10 floors, March to November 2025
  • Scope: 2,000 sit-stand trader desks, monitor arms, power and data provisions, plus all associated storage
Barclays Northampton - Trading Floor Desk Installation

Trusted by

Brand logo
Brand logo
Brand logo
Brand logo
Brand logo
Brand logo
Brand logo
Brand logo
trading_floor_installations_7df90fea-c68a-4f6a-9fc9-3d226c9df9e5

The Project

Teknion contacted SFI to help them manage the installation side of a major furniture project for Barclays' Northampton site: 2,000 sit-stand trader desks, monitor arms and full power and data, spread across 10 floors of a building that needed to keep working throughout.

During the project, we helped them install 2,000 desks and all associated power, without needing to shut down the trading floor.

Running the job in phases

To help us achieve this, we split the project into 8 phases across the 10 floors, running from March to November 2025. Each phase covered a different area, so only one part of the building was out of action while the rest of the floor kept working around it.

Where storage came in

Part of the brief was managing all associated storage for the project. With 2,000 desks that needed to be delivered in phases, alongside monitor arms and all of the power components that go with them, the project needed a lot of management.

We held stock between phases so that the furniture only turned up when each floor was ready for it. This kind of project coordination is an extension of our warehousing and storage service, but is managed by our project teams.

The result

By November 2025, all 2,000 desks were installed across the full 10 floors, delivered in 8 phases without affecting Barclays day-to-day operations.

For Teknion, that meant one partner responsible for installation, storage and coordination on a project of this scale, with seamless delivery from start to finish.

If you're planning a large-scale office furniture installation project across a multi-floor or live commercial building, talk to our team about commercial furniture delivery and installation and how phased delivery and storage can be built around your business.

Contact Us

Complete the form and someone with be in contact straight away!

First name *

Last name *

Email *

Company

Phone number

How did you hear about us? *

Please share more details about your enquiry *